What is the construction process required to build an airfoil building?


Release time:

2023-07-17

In the current focus on environmental protection and efficiency, air membrane construction with short construction period, pollution-free absolute advantage from a host of building forms stand out, become a popular building. Within a short period of time, all kinds of air membrane gymnasium, air membrane environmental protection material yard, air membrane coal shed, air membrane storage, air membrane cabin laboratory and so on endless, air membrane is effectively used in all walks of life.

Do you know what air membrane construction steps you need to go through to build a qualified air membrane building? Beijing Xinyuan Yijia Membrane Structure Technology Co., Ltd. takes you to understand the air membrane construction process!

1. The air membrane construction site carries out civil construction according to the design drawings, and pre-embedded aluminium grooves and steel cable pre-embedded parts.

2. At the same time of on-site construction, the membrane unit is cut and discharged in the workshop, and heat-laminated and processed according to the node practice of the installation drawings.

3. Procurement, production and processing of inflatable equipment, control system, access control system, lighting system, membrane connection accessories, etc.

4. Clean up the site and prepare for air membrane installation.

5. Installation of revolving door, emergency door, air membrane inflation equipment and air membrane control system.

6. Lift the membrane unit into place and unfold and connect it to the foundation, connect the membrane units with aluminium alloy clamps, and connect and fix the periphery of the membrane unit into the aluminium groove on the foundation beam.

7. Connect and fix the longitudinal and transverse cable network according to the design drawings.

8. Carry out air membrane inflation and debugging, and check whether each air membrane equipment is working normally in this process at the same time.

9. After the completion of the inflatable, the head of the door at the soft connection fixed to the corresponding door frame.

10. Need to install thermal insulation cotton air membrane hall, the thermal insulation cotton installed, the installation of electrical lighting system.

11. Complete the installation of air membrane, project acceptance.